Originally Posted by kamee
A and B together can complete the work in 15 days, so (A+B)’s one day work = 1/15
If A alone can complete a work in 20 days then A's one day work =1/20
Let B alone can complete the work in x days , so B's one day work = 1/x
Now ,
(A+B)’s one day work = A’s one day work + B’s one day work
=> 1/15=1/20+1/x
=> 1/x= 1/15 - 1/20
=> 1/x = 1/60
=> x=60
Hence B alone can complete the work in 60 days
|
Thanks bro.
I got your point now.
|